4) Installation and pre-commissioning of a compressors and equipment of phase 13 (units 147, 148, 103& 143)

Progress  

Our Role

Client

Location

Project

Completed

  • Installation 5 units of Centrifuges compressors of units 147-148.
  • commissioning 2unit of Reciprocating compressor unit 103 A/B.
  • Installation 16 pcs  of Acc.
  • Installation 9 pcs of internal the vessel.
  • Over hall and alignment pumps unit 143.
  • Commissioning units 101, 103A/B, 143, 147/148.

Farab Co.

South Pars Gas field

Installation and pre-commissioning of a compressors